Skip to content

Structure for JIRA: Ideas

Thank you for visiting our feedback website! Feel free to vote or post your own ideas. Make sure you turn on the option to notify you about changes and comments in your account settings, so that you can stay updated about the progress of the ideas you’re interested in.

38 results found

  1. Presentation Mode for pausing redraw and updates, BIG fonts, make the sprints more obvious

    We would like a Presentation Mode for the Gantt chart view that does the following:

    1) Pauses all updates, no redraw, no refresh, no live changes

    2) Makes the fonts for sprint and calendar dates much larger and easier to read (this could also be an accessibility settings in Configuration)

    3) Make it faster and easier to see the sprints on the timeline think about color coding. Offer a way to toggle between calendar view and sprint view or faster navigation around the Gantt chart, like a "jump to sprint x" or a "zoom to details" button.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  2. Have an option to use Gantt attributes in formulas

    As a user I'd like to use Gantt attributes in formulas on Cloud

    6 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  3. Share lag values across all structures

    Dependencies are stored in Jira as linked issues, but there's no concept of "Lag" (eg: TaskB can only start 1w after TaskA finishes), so that's stored in the Gantt.

    We have a main structure/gantt for all work (so we can see full utilization and dependencies), and people create their own structures just to see their team's work in a specific format (possibly even changing resource attribute).

    PROBLEM: A user adds a dependency with lag in one structure, and the dependency shows up in the other structutre, but without the lag!

    SOLUTION: Be able to store lag info in Jira somewhere?…

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  4. Have a calculated "Slack" column

    Structure/Gantt should have a "Slack" column that shows the number of days/weeks that a task can be delayed before any task that depends on it is delayed.

    This is critical when viewing complex projects and needing to know what can be delayed when new work comes up or tasks take longer than expected.

    2 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  5. Show week numbers in calendar (date picker pop-up)

    Add the week numbers to the date picker pop-up when selecting dates in Gantt. Since what we currently use comes from Jira, when the date picker is from Structure itself, this could be implemented.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  6. Ability to automatically show blocked stories or features in RED

    I would like to make blocked stories and/or features visible in the gantt chart by showing them in RED or some other indicator where they stand out.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  7. Allow multiple slices to affect an item if they target different sections

    In the Gantt view, when using slices, it would be great if you could have "stacking" slices as long as they don't target the same section. For example, in one of my Structure views I have a slice that auto-configures Tasks to be Milestones if they have a date in a specific field. I also want to be able to color code all non-Epic items based on their status, which would be 4 other slices, but if I wanted to apply this to Milestone Tasks I would need to make 4 additional slices to accomplish that.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  8. Allow customization of the Appearance of Groups in Structure.Gantt

    I would like to be able to customize the Appearance of parents that are treated as groups. When that option is turned on, the parent becomes represented in the Gantt as a bracket. When I don't want to expand the structure to a level that includes the child tasks, I would like to see those brackets as bars.

    6 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  9. Set end date by dragging right edge in manual scheduling mode

    Currently when i drag right edge of task it change task effort automatically unless end date is manually entered in Task Detail Pane before dragging. I would like to keep same effort but change end date and duration.

    Both behaviors might be handy so some kind of setting might be helpful.

    3 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  10. show more bars for one issue in a row (use more than 2 datepicker fields)

    In our issues we use more datepicker fields, e.g. Start Phase 1, End Phase 1, Starte Phase 2, End Phase 2 and so on.

    I want to show that bars within structure gantt, so not only one bar for one issue but several bars next to each other for one issue to show that time periods.

    5 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  11. Possibility to change the start and the end dates of the entire project

    Our organization would like to have a possibility to change the start and the end dates of the entire project. In this way, we could have a big picture view of all our projects in the timeline.

    13 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    under review  ·  0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  12. Milestone Trend Analysis

    Since it is possible to create milestones, I am wondering if there is a possibility to track and analyses the trend of milestones? Like or similar to a milestone-trend-analysis

    3 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    accepted  ·  1 comment  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  13. Allow dependency linking to tasks not in the Gantt view

    When trying to create a new dependency link for an item by clicking on the little dot beside the item in Gantt view it would be beneficial to be able to link to items which are not visible in the Gantt view. This is especially useful when using transforms which may filter items from the view but you still want to link to the hidden items.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  14. Reduce the margin/padding of every row to increase the level of entries visible in the screen

    Gantt charts are a good tools to see the globality of the project at once.
    Having a layout mode like: compact/confortable would be very interesting to maximized the visible content while looking at the dependencies in the gantt chart.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  15. Toggle to hide group indicator in Gantt view

    We have a number of Structures that are primarily used for program/portfolio high level views using the Gantt chart. These have a lot of groups and it can sometimes be visually distracting having all of the group indicators in the Gantt view, so it would be nice to have a way to toggle them on and off fairly easily; I think the "Gantt chart display options" menu would be a great place to put this toggle.

    3 votes
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  16. Allow multiple resource to work on one item

    As a user I would like to have more than one resource to work on a task, especially when doing macro planning and integration task that require multiple team to work together in one item.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  17. Improve Sandbox feature capabilities

    Latest version of sandbox with 3.0.1 is limited in its re-planning capabilities. Some changes require removing tasks and adding new tasks for change requests from Marketing. Need to add support for:

    Changing links between tasks
    Ability to add new tasks as a change requests and change linkage between resources
    Ability to remove tasks as a trade off for a change request
    Move tasks between groupings and relink with other tasks because of unexpected issues

    In all cases, most changes are to view how a change request or trade will effect a schedule before marketing and team commits to the changes.…

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  18. Be able to print issues attributes summed over time

    As a user I would like to monitor the evolution over time of a numerical issue attribute value summed across issues and displayed it like ressource usage are displayed.

    Example : attribute cost of a story to monitor cashflow over time.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  19. Posibillity to shift more issues at once in the timeline

    Our organization would like to have a feature which would let us to move few issues at once. F.e.:
    Epic has issues inside. So if I move the Epic bar, all those issues inside epic would move the same. Like in Jira's Advanced Roadmaps

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    accepted  ·  Viacheslav Ermolaev responded

    Thank you for your suggestion. This feature is frequently requested, and we hope to start working on it soon. If there’s something we can help you with, fell free to ask.

  20. Track a chain of linked issues

    You want to track a chain of linked (dependent) issues through a large structure. It would be useful to highlight predecessors and succesors of a given issue by issue link using, for example, colors.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    accepted  ·  0 comments  ·  Gantt  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
← Previous 1
  • Don't see your idea?

Structure for JIRA: Ideas

Categories

Feedback and Knowledge Base