Progress Bar changes color by ontime or overdue
Allowing users a quick view of the status for more than completion percentage for [insert your object of choice] if they are overdue or nearing completion deadlines
![](https://secure.gravatar.com/avatar/d8fdd44b2c9c4010b7e8c7c528dc7be7?size=40&default=https%3A%2F%2Fassets.uvcdn.com%2Fpkg%2Fadmin%2Ficons%2Fuser_70-6bcf9e08938533adb9bac95c3e487cb2a6d4a32f890ca6fdc82e3072e0ea0368.png)
collecting requirements — see comments
-
Hi Tyler,
Thanks for your suggestion! That makes a lot of sense, but in order to check the progress against time, we need to understand the start and the end dates of a task or a task group. What's more, we'll need to understand the work calendar to exclude weekends and holidays.
A part of this feature is coming soon with Gantt Chart extension, where a progress will be clearly seen on the time line. After that we'll see if we can show the "on time / delayed" marker in the table too.
Thanks!
Igor