when auto scheduling in gantt, have start and finish dates synced with a field in issue.
when auto scheduling in gantt, start and finish dates are not synced with Start Date and End Date of the issue and later when generating reports, we cant have a realistic report
5
votes

Hello Zarei!
Starting from Structure.Gantt 2.3 it is now possible to sync Gantt start and finish dates back into Jira.
See more details in Structure.Gantt 2.3 Release Notes: https://wiki.almworks.com/x/4IAUBQ