I think Haroon keeps in mind auto changing of DueDate for all tasks linked as "Depends on". something like changing of End Date for all related with main task(as it is in the MS Project )
in Jira I think need the folowing:
- if DueDate is updated for task 1 then need update DueDates for all tasks, linked to task 1 as "Depends on"( example: when task 1 "depends on" task xxx, task yyy then need update DueDate in the xxx, task yyy)
- how to update:
-- Dif = new DueDate of task 1 - old DueDate of task 1
-- set DueDate of task xxx = current Duedate of task xxx + Dif
-- set DueDate of task yyy = current Duedate of task yyy + Dif
I think Haroon keeps in mind auto changing of DueDate for all tasks linked as "Depends on". something like changing of End Date for all related with main task(as it is in the MS Project )
in Jira I think need the folowing:
- if DueDate is updated for task 1 then need update DueDates for all tasks, linked to task 1 as "Depends on"( example: when task 1 "depends on" task xxx, task yyy then need update DueDate in the xxx, task yyy)
- how to update:
-- Dif = new DueDate of task 1 - old DueDate of task 1
-- set DueDate of task xxx = current Duedate of task xxx + Dif
-- set DueDate of task yyy = current Duedate of task yyy + Dif