    accepted  ·  Alexey Pegov responded

    Hi Michael!

    You’re right, starting from Jira 8.3 it is now possible to specify dates for future sprints, we’re going to support this in one of upcoming releases!

    Thank you for feedback!

    An error occurred while saving the comment
    Eric Brown commented  · 

    Hi Alexey,
    This sprint problem is preventing us from fully using the Gantt view in agile mode. Has there been progress on the support of future dates?
    Thanks!

    Eric Brown supported this idea  · 